A project manager estimates that a project will take
x hours to complete, where x > 100. The goal is for
the estimate to be within 10 hours of the time it will
actually take to complete the project. If the manager
meets the goal and it takes y hours to complete the
project, which of the following inequalities
represents the relationship
between the estimated
time and the actual completion time?


Plisss some one can help me!!!

A project manager estimates that a project will take
x hours to co

ansver
Answers: 2

Another question on Mathematics

question
Mathematics, 21.06.2019 16:30
Hi my sisters and brothers can tell me the answer because i don’t understand the question
Answers: 1
question
Mathematics, 21.06.2019 22:30
What number is 7 units left of -15?
Answers: 1
question
Mathematics, 22.06.2019 01:00
The table showed price paid per concert ticket on a popular online auction site. what was the average price paid per ticket
Answers: 1
question
Mathematics, 22.06.2019 04:10
What is the slope-intercept from of the equation y+5=4(x+8)?
Answers: 2
You know the right answer?
A project manager estimates that a project will take
x hours to complete, where x > 100. Th...
Questions
question
Mathematics, 08.11.2020 14:00
question
Social Studies, 08.11.2020 14:00
question
English, 08.11.2020 14:00
question
Mathematics, 08.11.2020 14:00
question
English, 08.11.2020 14:00
question
Health, 08.11.2020 14:00
question
Mathematics, 08.11.2020 14:00
question
Biology, 08.11.2020 14:00
question
Social Studies, 08.11.2020 14:00
Questions on the website: 13722363