Mathematics, 07.10.2020 21:01 kahliey

Hi, I have a question about the following question. How many more employees have to be on team that will work on project A if the company wants to finish project within 72 days?

In the actual assignment, there was a table and you had to use the information from the table, so let me share the info from the table below (probably not all information is relevant for this question):

Project A Overview

No employees: 18

No of days: 95

Budgeted spend ($): 32000

Actual spend ($): 30000

Question: How many more employees have to be on team that will work on project A if the company wants to finish project within 72 days?

The answer suggested is: (18*95)/72 = 23.75 ( -> rounded ca. 24); 24 - 18 = 6 -> 6 employees have to join.

I really dont understand this logic. I dont understand why you can calculate 18 employees * 95 days if 95 days are the total project days.

I would have started like this:

No of days 95/ No of employees 18 = 5.27

5.27 * 72 days = 379.44

Difference:

379.44 - 18 = 361.44

I know the correct answer, which is 6 more employees, and even from a logical perspective, 361.44 looks way too big... they certainly dont need that many people. But I dont know how to calculate it to get 6 employees.

Could you please:

- Explain me this logic or

- Share an alternative calculation to derive to the correct answer?

Please help. Thank you so much.

ansver
Answers: 1

Another question on Mathematics

question
Mathematics, 21.06.2019 17:00
For the rule of 78, for a 12-month period, the last term in the sequence is 12 and the series sums to 78. for an 10 month period, the last term is and the series sum is . for a 15 month period, the last term is and the series sum is . for a 20 month period, the last term is and the series sum is
Answers: 2
question
Mathematics, 21.06.2019 17:30
Student price tickets to a movie are $1 and non student tickets are $2. 350 tickets are sold and the total amount made is $450. how many non student tickets were sold ? a) 100 b) 150 c) 200 d)250
Answers: 2
question
Mathematics, 21.06.2019 19:00
The weekly revenue for a company is r = 3p^2 + 60p + 1060, where p is the price of the company's product. what price will result in a revenue of $1200.
Answers: 1
question
Mathematics, 21.06.2019 19:30
Click the arrows to advance or review slides. mapping carbohydrates to food carbohydrates (grams) 15 food (quantity) bread (1 slice) pasta (1/3 cup) apple (1 medium) mashed potatoes (1/2 cup) broccoli (1/2 cup) carrots (1/2 cup) milk (1 cup) yogurt (6 oz.) 12 12 is jennifer's relation a function? yes no f 1 of 2 → jennifer figure out the difference between a function and a relation by answering the questions about her food choices
Answers: 2
You know the right answer?
Hi, I have a question about the following question. How many more employees have to be on team that...
Questions
question
Computers and Technology, 20.07.2019 00:20
question
Engineering, 20.07.2019 00:20
Questions on the website: 13722362