A project consists of 8 activities. The activity completion times and the precedence relationships are as follows: Activity. Completion time Days. immediate predecessor activities.

A. 5 -
B. 7 -
C. 6 -
D. 3 A
E. 4 B, C
F. 2 C
G. 6 A, D
H. 5 E, F

1. Draw the network diagram using AON model notations:

2. What is the critical path?

3. Calculate: Early Start, Early finish, Late start, Late finish, slack, critical path.

4. What is the minimum time to complete the projects?

1. If activity E is delayed by 3 days how is the project completion time affected? Why is this the case?

2. If activity F is delayed by 3 days how is the project completion time affected? Why is this the case? Will the critical path change, why or why not?

3. If you want to shorten (crash) the overall time of this project, how do you pick which activity to shorten? What information, if any, do you need?

4. Once you shorten (crash) an activity, do you need to redo the AON, yes or no? Why or why not?

ansver
Answers: 3

Another question on Mathematics

question
Mathematics, 21.06.2019 17:50
Find the cosine function that is represented in the graph.
Answers: 1
question
Mathematics, 21.06.2019 18:30
Which representation has a constant of variation of -2.5
Answers: 1
question
Mathematics, 21.06.2019 20:40
The roots of the function f(x) = x2 – 2x – 3 are shown. what is the missing number?
Answers: 2
question
Mathematics, 21.06.2019 21:00
Ftara spends $219 a month for her car payment and she makes $3,200 a month, what percent of her monthly income is spent on her car payment?
Answers: 2
You know the right answer?
A project consists of 8 activities. The activity completion times and the precedence relationships a...
Questions
question
Mathematics, 11.03.2020 05:40
question
Mathematics, 11.03.2020 05:40
Questions on the website: 13722363