Mathematics, 20.10.2020 16:01 kkingstone453

The critical path for a project was found to be 37 days. The variances total 27. What is probability of completing in 43 days? Below is information that might be useful to answer the question. Answer to 2 decimal points

ansver
Answers: 1

Another question on Mathematics

question
Mathematics, 21.06.2019 18:00
Express in the simplest form: (x^2+9x+14/x^2-49) / (3x+6/x^2+x-56)
Answers: 3
question
Mathematics, 21.06.2019 18:10
What is the value of x in the following equation. -x ^3/2 = -27
Answers: 1
question
Mathematics, 21.06.2019 22:00
Let event a = you roll an even number on the first cube.let event b = you roll a 6 on the second cube.are the events independent or dependent? why?
Answers: 1
question
Mathematics, 21.06.2019 22:30
Tommy buys a sweater that is on sale for 40% off the original price. the expression p -0.4p can be used to find the sale price of the sweater, where p is the original price of the sweater. if the original price of the sweater is 50, what is the sale price?
Answers: 1
You know the right answer?
The critical path for a project was found to be 37 days. The variances total 27. What is probability...
Questions
question
Mathematics, 10.03.2021 08:10
question
Mathematics, 10.03.2021 08:10
question
Mathematics, 10.03.2021 08:10
question
Biology, 10.03.2021 08:10
question
Business, 10.03.2021 08:10
question
History, 10.03.2021 08:10
question
Mathematics, 10.03.2021 08:10
question
Physics, 10.03.2021 08:10
question
Law, 10.03.2021 08:10
Questions on the website: 13722362