Mathematics, 23.10.2020 09:01 baileymtamayo

A job can be completed in 30 days by 12 men. If the job is required to be completed in 12 days earlier, how many more men are required
if they are working at the same rate?

ansver
Answers: 1

Another question on Mathematics

question
Mathematics, 21.06.2019 20:00
The multiplicative property of equality states that for real numbers a, b, c, and d, if a = b and c = d, then ac = bd. true false
Answers: 1
question
Mathematics, 21.06.2019 22:40
Awoman has 14 different shirts: 10 white shirts and 4 red shirts. if she randomly chooses 2 shirts to take with her on vacation, then what is the probability that she will choose two white shirts? show your answer in fraction and percent, round to the nearest whole percent.
Answers: 3
question
Mathematics, 21.06.2019 23:00
An elevator travels 310 feet in 10 seconds. at that speed, how far can't his elevator travel in 12 seconds?
Answers: 1
question
Mathematics, 22.06.2019 00:00
The width of a rectangle is half as long as the length. the rectangle has an area of 18 square feet. what are the length and width of the rectangle?
Answers: 1
You know the right answer?
A job can be completed in 30 days by 12 men. If the job is required to be completed in 12 days earl...
Questions
question
Social Studies, 17.11.2019 10:31
question
Mathematics, 17.11.2019 10:31
question
Biology, 17.11.2019 10:31
Questions on the website: 13722367