4 men can finish a job in 7 days how many more people are needed to finish the job in 4 days? plz give explanation

ansver
Answers: 1

Another question on Mathematics

question
Mathematics, 20.06.2019 18:04
Which operation should be performed first according to the order of operations? 44 • 2 – [(5 + 20 • 3) – 12] + 16 ÷ 2 5 + 20 20 • 3 16 ÷ 2 44 • 2
Answers: 2
question
Mathematics, 21.06.2019 17:30
What is the greater volume 72 quarts or 23 gallons
Answers: 1
question
Mathematics, 21.06.2019 20:30
10 points? me . its important ‼️‼️
Answers: 1
question
Mathematics, 22.06.2019 02:30
Find the difference in area between the circle and the triangle. click on the answer until the correct answer is showing.possible answers: a = 4 pi - 8a = 9 pi - 9/2 √3a = 16/3 pia = 16a = 27 pi
Answers: 1
You know the right answer?
4 men can finish a job in 7 days how many more people are needed to finish the job in 4 days? plz g...
Questions
question
Mathematics, 17.04.2020 20:58
question
Mathematics, 17.04.2020 20:58
question
Mathematics, 17.04.2020 20:58
question
Mathematics, 17.04.2020 20:59
Questions on the website: 13722367