To finish a certain job in 8 days, 6 workers are needed. If it is required to finish the same job in 2 days advance, how many workers have to work? * 8 points

ansver
Answers: 2

Another question on Mathematics

question
Mathematics, 21.06.2019 17:00
Which point lies on a circle with a radius of 5 units and center at p(6, 1)?
Answers: 1
question
Mathematics, 21.06.2019 18:30
If the value of x increases by 5, how does the value of m(x + 3) change? a) it increases by 5m. b) it increases by 8m. c) it decreases by 5m. d) it decreases by 8m.
Answers: 1
question
Mathematics, 21.06.2019 21:30
Money off coupons have been circulated to 300 households. only 2/5 of these were redeemed (used) in the local supermarket to get a free shampoo. what fraction of coupons were unused? (ps: write how you got the answer)
Answers: 1
question
Mathematics, 21.06.2019 22:00
The difference of two numbers is 40. find the numbers if 0.3 parts of one number is equal to 37.5% of the other one.
Answers: 1
You know the right answer?
To finish a certain job in 8 days, 6 workers are needed. If it is required to finish the same job in...
Questions
question
Mathematics, 20.08.2019 23:30
question
Biology, 20.08.2019 23:30
question
Mathematics, 20.08.2019 23:30
Questions on the website: 13722367