If 20 assemblers can complete a certain job in 6 hours, how long will the same job take if the number of assemblers is cut back to 12?

ansver
Answers: 1

Another question on Mathematics

question
Mathematics, 21.06.2019 12:30
Np4=12np2 with clear explanation.
Answers: 2
question
Mathematics, 21.06.2019 14:00
Ben bowled 124 and 188 in his first two games. what must he bowl in his third game to have an average of at least 160?
Answers: 1
question
Mathematics, 21.06.2019 19:30
Order the measurements from the least to the greatest. 2,720 ml , 24.91 l , 0.0268 kl
Answers: 1
question
Mathematics, 21.06.2019 22:00
If abcde is reflected over the x-axis and then translated 3 units left, what are the new coordinates d? are he re
Answers: 1
You know the right answer?
If 20 assemblers can complete a certain job in 6 hours, how long will the same job take if the numbe...
Questions
question
Mathematics, 09.03.2021 20:30
question
Mathematics, 09.03.2021 20:30
question
Mathematics, 09.03.2021 20:30
question
Mathematics, 09.03.2021 20:30
question
Mathematics, 09.03.2021 20:30
question
History, 09.03.2021 20:30
Questions on the website: 13722362