The following information relates to a project (task times are in weeks). What is the probability that the project can be completed within weeks? What is the probability that the project will take longer than weeks?

ansver
Answers: 1

Another question on Mathematics

question
Mathematics, 21.06.2019 16:30
Beth makes batches of bluberry muffins and banna muffins. each batchis 6 muffins. she makes 2.5 batches of bluberry muffins. how many batches of bananna muffins should beth make if she wants to have a total of 60 muffins?
Answers: 1
question
Mathematics, 21.06.2019 16:50
Which of the following points is collinear with (-2,1) and (0,3)
Answers: 3
question
Mathematics, 21.06.2019 19:00
If (x-2) 2= 49, then x could be a. -9 b. -7 c.- 2 d. 5 e.9
Answers: 2
question
Mathematics, 21.06.2019 22:30
Sketch the vector field vector f( vector r ) = 8vector r in the xy-plane. select all that apply. the length of each vector is 8. the lengths of the vectors decrease as you move away from the origin. all the vectors point away from the origin. all the vectors point in the same direction. all the vectors point towards the origin. the lengths of the vectors increase as you move away from the origin.
Answers: 2
You know the right answer?
The following information relates to a project (task times are in weeks). What is the probability th...
Questions
question
World Languages, 05.03.2021 22:00
Questions on the website: 13722360