BRAINLIEST 10 MINS Ed is managing a construction project. The function y = 0.75x represents the percentage of work done in terms of the number of weeks since the project started.

The value 0.75 represents

The function representing the percentage of work that remains in terms of the number of weeks since the project started is y = (the percentage of work done , the number of weeks since the work started , the percentage of work done each week.) − (75 , 0.75 , 0 , 100) x.

ansver
Answers: 3

Another question on Mathematics

question
Mathematics, 21.06.2019 16:30
Question 5 spring semester final exam math evaluate
Answers: 2
question
Mathematics, 21.06.2019 17:00
According to modern science, earth is about 4.5 billion years old and written human history extends back about 10,000 years. suppose the entire history of earth is represented with a 10-meter-long timeline, with the birth of earth on one end and today at the other end.
Answers: 2
question
Mathematics, 21.06.2019 18:10
True or false look at the picture pls : /
Answers: 2
question
Mathematics, 21.06.2019 20:00
The diagram shows corresponding lengths in two similar figures. find the area of the smaller figure. a. 14.4 yd2 b. 24 yd2 c. 26.4 yd2 d. 28
Answers: 1
You know the right answer?
BRAINLIEST 10 MINS Ed is managing a construction project. The function y = 0.75x represents the per...
Questions
question
Mathematics, 26.02.2021 03:10
question
Mathematics, 26.02.2021 03:10
question
Mathematics, 26.02.2021 03:10
question
Mathematics, 26.02.2021 03:10
question
Mathematics, 26.02.2021 03:10
Questions on the website: 13722363