To complete a task in 16 days a company needs
5 people each working for 6 hours per day.
The company decides to have
8 people each working for 4 hours per day.
Assuming that each person works at the same rate,
how many days will the task take to complete?


Question Progress

Homework Progress
88 / 213 Marks
To complete a task in 16 days a company needs

ansver
Answers: 3

Another question on Mathematics

question
Mathematics, 21.06.2019 18:50
The volume of a cone is 37x3 cubic units and its height is x units. which expression represents the radius of the cone's base, in units? 1 s o 3x o 6x obx 93x2
Answers: 1
question
Mathematics, 21.06.2019 22:30
Which of the following circles have their centers in the third quadrant? check all that apply.
Answers: 1
question
Mathematics, 22.06.2019 01:00
At a book fair, joe bought 24 books at 3 for $5 and had $2 left. how much money did he have at first?
Answers: 2
question
Mathematics, 22.06.2019 01:30
Urgent need asap △abc is similar to △xyz. also, side ab measures 6 cm, side bc measures 18 cm, and side xy measures 12 cm. what is the measure of side yz ? enter your answer in the box.
Answers: 1
You know the right answer?
Question Progress Homework Progress
88 / 213 Marks
To complete a task in 16 days a comp...
Questions
question
Mathematics, 05.11.2020 05:50
question
Mathematics, 05.11.2020 05:50
question
Mathematics, 05.11.2020 05:50
question
Mathematics, 05.11.2020 05:50
question
History, 05.11.2020 05:50
question
Mathematics, 05.11.2020 05:50
question
Spanish, 05.11.2020 05:50
Questions on the website: 13722360