W The number of days, d, to build a house is given by
780
d =
where w is the number of workers used each day on site.
Bob's company will take 60 days to build the house.
Pat's company will take 39 days to build the house.
Pat's company will have to use more workers each day than Bob's company.
How many more?
Note: Make your final answer clear by writing "... more".

ansver
Answers: 1

Another question on Mathematics

question
Mathematics, 21.06.2019 20:10
Which value of m will create a system of parallel lines with no solution? y = mx - 6 8x - 4y = 12
Answers: 3
question
Mathematics, 21.06.2019 23:30
Petes dog weighed 30 pounds it then lost 16% of it's weight how much did pete lose
Answers: 2
question
Mathematics, 22.06.2019 02:20
Of the 27 players trying out for the school basketball team, 8 are more than 6 feet tall and 7 have good aim. what is the probability that the coach would randomly pick a player over 6 feet tall or a player with a good aim? assume that no players over 6 feet tall have good aim. a. b. c. d.
Answers: 1
question
Mathematics, 22.06.2019 03:00
At a soccer tournament 1212 teams are wearing red shirts, 66 teams are wearing blue shirts, 44 teams are wearing orange shirts, and 22 teams are wearing white shirts. for every 22 teams at the tournament, there is 1 team wearing shirts. choose 1
Answers: 2
You know the right answer?
W The number of days, d, to build a house is given by
780
d =
where w is the numb...
Questions
question
Mathematics, 09.04.2021 18:20
question
Arts, 09.04.2021 18:20
question
English, 09.04.2021 18:20
question
Mathematics, 09.04.2021 18:20
question
History, 09.04.2021 18:20
question
Mathematics, 09.04.2021 18:20
Questions on the website: 13722360