When building a house, the number of days required to build varies inversely with with the number of workers. One house was built in 29 days by 24 workers. How many days would it take to build a similar house with 4 workers?

ansver
Answers: 3

Another question on Mathematics

question
Mathematics, 21.06.2019 15:30
The coordinates of a, b, and c in the diagram are a(p,4), b(6,1), and c(9,q). which equation correctly relates p and q? hint: since is perpendicular to , the slope of × the slope of = -1. a. p - q = 7 b. q - p = 7 c. -q - p = 7 d. p + q = 7
Answers: 3
question
Mathematics, 21.06.2019 17:10
Which of the following expressions is equal to 2x^2+8
Answers: 1
question
Mathematics, 21.06.2019 23:30
Consider the first four terms of the sequence below. what is the 8th term of this sequence?
Answers: 1
question
Mathematics, 22.06.2019 00:10
Change negative exponents to positive, then solve
Answers: 1
You know the right answer?
When building a house, the number of days required to build varies inversely with with the number of...
Questions
question
Chemistry, 25.02.2021 19:50
question
Mathematics, 25.02.2021 19:50
question
Mathematics, 25.02.2021 19:50
Questions on the website: 13722360