The number of days, d, to build a house is given by
780
d =
W
where w is the number of workers used each day on site.
Bob's company will take 60 days to build the house.
Pat's company will take 39 days to build the house.
Pat's company will have to use more workers each day than Bob's company.
How many more?
Answers: 3
Mathematics, 21.06.2019 18:00
Since opening night, attendance at play a has increased steadily, while attendance at play b first rose and then fell. equations modeling the daily attendance y at each play are shown below, where x is the number of days since opening night. on what day(s) was the attendance the same at both plays? what was the attendance? play a: y = 8x + 191 play b: y = -x^2 + 26x + 126
Answers: 1
Mathematics, 21.06.2019 19:00
Billy plotted −3 4 and −1 4 on a number line to determine that −3 4 is smaller than −1 4 is he correct? explain why or why not?
Answers: 3
Mathematics, 22.06.2019 00:30
On her first stroke, maya hit a golf ball 146 yards, 2 feet, 11 inches. on her second stroke, she hit it 163 yards, 1 foot, 2 inches. how far did the ball go all together? convert the answer to larger units whenever possible.
Answers: 2
Mathematics, 22.06.2019 01:30
Awoman who is 64 inches with a shoulder width of 16 inches. write an equation relating the height h to the width w. find the height of a woman who has ashoulder width of 18.5 inches
Answers: 3
Chemistry, 04.02.2020 18:55
Chemistry, 04.02.2020 18:55
Chemistry, 04.02.2020 18:55
Mathematics, 04.02.2020 18:55
Social Studies, 04.02.2020 18:55
Mathematics, 04.02.2020 18:55
Mathematics, 04.02.2020 18:55
Mathematics, 04.02.2020 18:55