A house needs to be built and ready to move into by June 1 st . It takes 1 week to clear the land. After that, it takes 4 days to lay the foundation. It takes 2 ½ weeks to put up the framing of the house. The interior of the house will take 9 days to finish. When should the crew start work on the house? BTW this is middle school my stuff says i am in college :(