A house needs to be built and ready to move into by June 1 st . It takes 1 week to clear the land. After that, it takes 4 days to lay the foundation. It takes 2 ½ weeks to put up the framing of the house. The interior of the house will take 9 days to finish. When should the crew start work on the house?

ansver
Answers: 3

Another question on Mathematics

question
Mathematics, 21.06.2019 18:30
Two cyclists 84 miles apart start riding toward each other at the same. one cycles 2 times as fast as the other. if they meet 4 hours later, what is the speed (in mi/h) of the faster cyclist?
Answers: 1
question
Mathematics, 21.06.2019 23:00
Mike wants to make meatloaf. his recipe uses a total of 8 pounds of meat. if he uses a 3 to 1 ratio of beef to pork, how much pork will he use? enter your answer as a mixed number in simplest terms.
Answers: 1
question
Mathematics, 21.06.2019 23:00
Which of the following graphs could represent a cubic function?
Answers: 1
question
Mathematics, 22.06.2019 01:00
Y= x – 6 x = –4 what is the solution to the system of equations? (–8, –4) (–4, –8) (–4, 4) (4, –4)
Answers: 1
You know the right answer?
A house needs to be built and ready to move into by June 1 st . It takes 1 week to clear the land. A...
Questions
question
Biology, 01.04.2021 16:50
question
Social Studies, 01.04.2021 16:50
Questions on the website: 13722359