Mathematics, 15.02.2021 20:10 alexis9658

You own a hot-mix asphalt plant and must provide asphalt for two construction sites tomorrow using two different asphalt mixes. The first site is an airport runway project with a much more demanding pavement design, whereas the second site is a residential neighborhood using a fairly typical asphalt mix. The airport project is also more profitable than the residential project. The resource requirements for each mix type are shown below: Binder Polymer Profit
(per ton) (per ton) (S per ton)
Airport Mix 23 9 85
Residential Mix 12 2 30
You need to decide how many tons of each mix type produce Your small batch plant has a of 25 tons of hot-mix asphalt per day. Further, you have only 425 units of binder capacity additive. You are contracted to deliver at least s tons available and 125 units of polymer of airport mix and at least 13 tons of residential mix. You dedde to use a linear program (LP) to In nur derisinn How would you organize your LP?

ansver
Answers: 1

Another question on Mathematics

question
Mathematics, 21.06.2019 18:00
When lulu enlarged her drawing of a rabbit, the enlarged picture appeared to be distorted. which statement about the transformation applied to her drawing is true?
Answers: 2
question
Mathematics, 21.06.2019 21:00
3x + 4y = 5 x- 3y = -7 solve by substitution
Answers: 1
question
Mathematics, 21.06.2019 22:30
What is the point slope form of a line with slope -5 that contains point (2,-1)
Answers: 1
question
Mathematics, 21.06.2019 23:10
Carly stated, “all pairs of rectangles are dilations.” which pair of rectangles would prove that carly’s statement is incorrect?
Answers: 1
You know the right answer?
You own a hot-mix asphalt plant and must provide asphalt for two construction sites tomorrow using t...
Questions
question
Biology, 06.05.2020 02:46
question
Mathematics, 06.05.2020 02:46
question
Mathematics, 06.05.2020 02:46
Questions on the website: 13722361