subject
Mathematics, 15.02.2021 21:50 payshencec21

A front-end loader is to load trucks with granular material that has a swell factor of 15%. If the loader has a heaped capacity of 10 cu. yd., calculate the total cycle time for the loader if it can move 55 cu. yd. of in-bank material in 1 hr. with an efficiency of 48 min./hr.

ansver
Answers: 2

Another question on Mathematics

question
Mathematics, 21.06.2019 17:00
Ataxi company charges $2.25 for the first mile and then $0.20 per mile for each additional mile, or f = $2.25 + $0.20(m - 1) where f is the fare and m is the number of miles. if juan's taxi fare was $6.05, how many miles did he travel in the taxi? if juan's taxi fare was 7.65, how many miles did he travel in taxi
Answers: 1
question
Mathematics, 22.06.2019 02:00
The table below shows the number of free throw shots attempted and the number of shots made for the five starting players on the basketball team during practice. each player's goal is to make 80% of her shots.
Answers: 1
question
Mathematics, 22.06.2019 02:30
Joyce deposited $5000 in an account with an annual interest rate of 6%, compounded annually. how much money will be in the account 10 years later
Answers: 2
question
Mathematics, 22.06.2019 02:50
Determine the following data for the quadratic relation f(x) = -3(x+2)(x-3)? i. direction of opening: ii. x-intercepts: iii. y-intecept: iv. axis of symmetry: v. vertex:
Answers: 3
You know the right answer?
A front-end loader is to load trucks with granular material that has a swell factor of 15%. If the l...
Questions
question
English, 18.08.2019 15:00
Questions on the website: 13722367