Mathematics, 18.03.2021 02:20 phirejz6402

Si 27 hombres terminan una obra en 16 días, ¿cuántos hombres se necesitarán para terminar la obra en 24 días?

ansver
Answers: 3

Another question on Mathematics

question
Mathematics, 21.06.2019 17:30
Which of the following is true about the graph of f(x)=7^x. select all that apply. a= it intercepts the x axis b=it intercepts both axis c=it intercepts neither d=it intercepts the y axis
Answers: 1
question
Mathematics, 21.06.2019 20:00
How many grams the dog will eat in 3 days?
Answers: 1
question
Mathematics, 21.06.2019 20:30
What is the difference between the equations of a vertical and a horizontal line?
Answers: 2
question
Mathematics, 21.06.2019 20:30
Evaluate 8j -k+148j−k+14 when j=0.25j=0.25 and k=1k=1.
Answers: 1
You know the right answer?
Si 27 hombres terminan una obra en 16 días, ¿cuántos hombres se necesitarán para terminar la obra en...
Questions
question
Mathematics, 16.12.2020 22:00
question
Mathematics, 16.12.2020 22:00
question
Mathematics, 16.12.2020 22:00
question
English, 16.12.2020 22:00
question
Mathematics, 16.12.2020 22:00
Questions on the website: 13722362