When building a house, the number of days required to build varies inversely with with the number of workers. One house was built in 19 days by 28 workers. How
many days would it take to build a similar house with 7 workers?

ansver
Answers: 3

Another question on Mathematics

question
Mathematics, 21.06.2019 12:30
Use the function nest to evaluate p(x) = 1 + x + · · · + x50 at x = 1.00001. (use the matlab ones command to save typing.) find the error of the computation by comparing with the equivalent expression q(x) = (x51 − 1)/(x − 1).
Answers: 3
question
Mathematics, 21.06.2019 17:30
Monthly water bills for a city have a mean of $108.43 and a standard deviation of $32.09. find the probability that a randomly selected bill will have an amount greater than $155, which the city believes might indicate that someone is wasting water. would a bill that size be considered unusual?
Answers: 2
question
Mathematics, 21.06.2019 19:00
There is an entrance to the computer room at point e which lies on ab and is 5 feet from point a. plot point e on the coordinate plane. find the distance from the entrance at point e to the printer at point e
Answers: 1
question
Mathematics, 21.06.2019 20:10
Which value of m will create a system of parallel lines with no solution? y= mx - 6 8x - 4y = 12
Answers: 1
You know the right answer?
When building a house, the number of days required to build varies inversely with with the number o...
Questions
question
History, 09.10.2020 21:01
question
Mathematics, 09.10.2020 21:01
question
Mathematics, 09.10.2020 21:01
Questions on the website: 13722362