12 workers can do a peice of work in 20 days. How many workers should be added to complete work in 16 days?​

ansver
Answers: 1

Another question on Mathematics

question
Mathematics, 21.06.2019 15:30
Simplify a7/a4 a) 1/a3 b)-a/a2 c)a4/a3 d)a3
Answers: 2
question
Mathematics, 21.06.2019 18:00
Which represents the solution set of the inequality 5x-9 < 21? a. x < 12/5 b. x > 12/5 c. x > 6 d. x < 6
Answers: 2
question
Mathematics, 21.06.2019 18:30
Mr. and mrs. wallace have decided to buy a car for $21,600. they finance $15,000 of it with a 5-year auto loan at 2.9% arp. what will be their monthly payment be? a. $268.20 b. $268.86 c. $269.54 d. $387.16 i need !
Answers: 1
question
Mathematics, 21.06.2019 19:00
[15 points, algebra 2]simplify the complex fraction and find the restrictions.
Answers: 1
You know the right answer?
12 workers can do a peice of work in 20 days. How many workers should be added to complete work in 1...
Questions
question
Mathematics, 08.01.2021 20:40
question
Mathematics, 08.01.2021 20:40
question
Mathematics, 08.01.2021 20:40
question
Chemistry, 08.01.2021 20:40
question
English, 08.01.2021 20:40
Questions on the website: 13722362