Engineers are digging a 3200-foot-long tunnel at a constant rate. After 5 months, the engineers still need to dig 1700 feet to finish the project. How much time does it take to complete the tunnel from start to finish? Will the engineers have enough time if the project was started in December 2020 and the deadline to finish the project was in August 2021? Please explain your answer for yes or no.

Hint:
y=mx+b (slope-intercept form)
x=time
y=distance
b=3200
Start & Finish: ??
Total length=3200ft
Left over=1700ft after 5 months of digging

ansver
Answers: 3

Another question on Mathematics

question
Mathematics, 21.06.2019 16:30
Its due ! write an equation in which the quadratic expression 2x^2-2x 12 equals 0. show the expression in factored form and explain what your solutions mean for the equation. show your work.
Answers: 1
question
Mathematics, 21.06.2019 18:00
Marla bought a book for $12.95, a binder for $3.49, and a backpack for $44.99. the sales tax rate is 6%. find the amount of tax and the total she paid for these items
Answers: 1
question
Mathematics, 21.06.2019 21:40
Use sigma notation to represent the following series for 9 terms.
Answers: 2
question
Mathematics, 21.06.2019 23:00
*segment an is an altitude of right ? abc with a right angle at a. if ab = 2root 5 in and nc = 1 in, find bn, an, ac.
Answers: 3
You know the right answer?
Engineers are digging a 3200-foot-long tunnel at a constant rate. After 5 months, the engineers stil...
Questions
question
Mathematics, 17.07.2019 16:00
question
Mathematics, 17.07.2019 16:00
question
Mathematics, 17.07.2019 16:00
Questions on the website: 13722367