Mathematics, 07.04.2021 06:00 iicekingmann

When constructing a fence at the park, it takes 10 workers 24 days to complete the job. How many workers are needed to complete the job in 20 days?

ansver
Answers: 3

Another question on Mathematics

question
Mathematics, 21.06.2019 17:00
What is the y intercept of f(x)=(1/2)^x?
Answers: 1
question
Mathematics, 21.06.2019 17:00
How to solve a simultaneous equation involved with fractions?
Answers: 1
question
Mathematics, 21.06.2019 20:00
Aball is dropped from a height of 10m above the ground. it bounce to 90% of its previous height on each bounce. what is the approximate height that the ball bounce to the fourth bounce?
Answers: 2
question
Mathematics, 21.06.2019 21:30
Ijust need these 2 questions answered (the second pic is just confirmation i'm not confident in that answer)
Answers: 1
You know the right answer?
When constructing a fence at the park, it takes 10 workers 24 days to complete the job. How many wo...
Questions
question
Mathematics, 18.08.2020 21:01
question
Mathematics, 18.08.2020 21:01
question
Spanish, 18.08.2020 21:01
question
Advanced Placement (AP), 18.08.2020 21:01
Questions on the website: 13722361