The following is a table of activities associated with
a project at rafay ishfaq’s software fi...
Mathematics, 18.11.2019 06:31 fendyli6066
The following is a table of activities associated with
a project at rafay ishfaq’s software firm in chicago, their durations,
and what activities each must precede:
activity duration (weeks) precedes
a (start) 1 b, c
b 1 e
c 4 f
e 2 f
f (end) 2 —
a) draw an aon diagram of the project, including activity durations.
b) define the critical path, listing all critical activities in chronological
order.
c) what is the project duration (in weeks)?
d) what is the slack (in weeks) associated with any and all noncritical
paths through the project?
Answers: 1
Mathematics, 21.06.2019 16:00
5,600 x 10^3 = a) 560 b) 5,000,600 c) 5,600,000 d) 56,000
Answers: 2
Mathematics, 21.06.2019 17:00
The sum of the reciprocal of a positive number and the reciprocal of 2 more than the number is 3/4 equation: the number is
Answers: 2
Mathematics, 21.06.2019 18:10
An initial investment of $100 is now valued at $150. the annual interest rate is 5%, compounded continuously. the equation 100e0.05t = 150 represents the situation, where t is the number of years the money has been invested. about how long has the money been invested? use your calculator and round to the nearest whole number. years
Answers: 3
Mathematics, 21.06.2019 21:00
Calculate the missing value. round the answer to on decimal place. start with 70, increase it by 21%, and end up with
Answers: 2
Computers and Technology, 29.01.2021 08:00
Mathematics, 29.01.2021 08:00
Chemistry, 29.01.2021 08:00
Chemistry, 29.01.2021 08:00
History, 29.01.2021 08:00
Mathematics, 29.01.2021 08:00
Mathematics, 29.01.2021 08:00
Mathematics, 29.01.2021 08:00
Mathematics, 29.01.2021 08:00
Mathematics, 29.01.2021 08:00
Mathematics, 29.01.2021 08:00