Using pert, adam munson was able to determine that the expected project completion time for the construction of a pleasure yacht is 21 months, and the project variance is 4. a) what is the probability that the project will be completed in 17 months? b) what is the probability that the project will be completed in 20 months? c) what is the probability that the project will be completed in 23 months? d) what is the probability that the project will be completed in 25 months? e) what is the due date that yields a 95% chance of completion?
Answers: 3
Mathematics, 21.06.2019 22:00
If rs 900 amounts to rs 1044 in 4 years, what sum will amount to 1368 in 3 1/2 years at the same rate
Answers: 3
Mathematics, 21.06.2019 22:30
Atotal of 766 tickets were sold for the school play. they were either adult tickets or student tickets. there were 66 more student tickets sold than adult tickets. how many adult tickets were sold?
Answers: 1
5/6k=-20 what is the correct answer ? ?...
Physics, 24.03.2022 04:20
Biology, 24.03.2022 04:20
Chemistry, 24.03.2022 04:20
Mathematics, 24.03.2022 04:20
Mathematics, 24.03.2022 04:20
Mathematics, 24.03.2022 04:30
Mathematics, 24.03.2022 04:30
Mathematics, 24.03.2022 04:30
Mathematics, 24.03.2022 04:30
Mathematics, 24.03.2022 04:40
Chemistry, 24.03.2022 04:40