There are four activities on the critical path, and they have standard deviations of 1, 2, 4, and 2. what is the probability that the project will be completed in 38 weeks if its expected completion time is 40 weeks?

ansver
Answers: 1

Another question on Mathematics

question
Mathematics, 21.06.2019 15:00
Part a: select all of the ordered pairs that are located on the graph of the equation. part b: does the graph of the equation represent a function? select all correct answers for part a and one answer for part b.
Answers: 2
question
Mathematics, 21.06.2019 23:30
When a valve is open 281 gallons of water go through it in one hour the number of gallons that would go through in 94 hours is
Answers: 1
question
Mathematics, 22.06.2019 00:00
Which choice names the hypotenuse of triangle xyz? a. segment yx b. segment yz c. segment ab d. segment zx
Answers: 3
question
Mathematics, 22.06.2019 00:30
Which equation can be solved to find one of the missing side lengths in the triangle? cos(60o) = cos(60o) = cos(60o) = cos(60o) = mark this and return
Answers: 3
You know the right answer?
There are four activities on the critical path, and they have standard deviations of 1, 2, 4, and 2....
Questions
question
History, 25.07.2019 17:40
Questions on the website: 13722360