18 -person road crew is scheduled to finish repairing a highway in 10 days. On the morning of the fifth day, several workers of the crew were moved to another project. How many workers were removed from the crew, if the rest of the crew finished the remaining repairs in 12 days?

ansver
Answers: 2

Another question on Mathematics

question
Mathematics, 21.06.2019 14:40
Farnesene is a sesquiterpene. how many different isomers arising from double-bond isomerizations are possible? g
Answers: 2
question
Mathematics, 21.06.2019 16:00
Select all the correct answers. what is 221,000,000,000,000,000,000 expressed in scientific notation?
Answers: 2
question
Mathematics, 21.06.2019 16:00
Angela rode his bike around a bike trail that was 1/4 of a mile long he rode his bike around the trail 8 * angelo says he wrote a total of 8/4 miles to russell says he's wrong and he actually and says that he actually wrote to my who is corrupt use words and trying to explain how you know.
Answers: 2
question
Mathematics, 21.06.2019 16:30
Asequence {an} is defined recursively, with a1 = 1, a2 = 2 and, for n > 2, an = an-1 an-2 . find the term a241. a) 0 b) 1 c) 2 d) 1 2
Answers: 1
You know the right answer?
18 -person road crew is scheduled to finish repairing a highway in 10 days. On the morning of the fi...
Questions
question
Mathematics, 16.12.2020 22:50
question
Arts, 16.12.2020 22:50
question
Chemistry, 16.12.2020 22:50
question
Business, 16.12.2020 22:50
question
Mathematics, 16.12.2020 22:50
question
Mathematics, 16.12.2020 22:50
question
Mathematics, 16.12.2020 22:50
Questions on the website: 13722367