If 4 labourers can finish a job in 6days how long would it take 3men to do the job

ansver
Answers: 1

Another question on Mathematics

question
Mathematics, 21.06.2019 14:50
What is the point-slope form of theequation for the line with a slope of-2 that passes through (1, 4)? a y + 1 = -2(x + 4)b y-1=-2(x-4)c y + 4 = -2(x + 1)d y - 4 = -2(x - 1)
Answers: 1
question
Mathematics, 21.06.2019 16:30
Which choice represents the sample space ,s for this event
Answers: 3
question
Mathematics, 21.06.2019 19:10
How many different three-digit numbers can be formed using the digits 1 comma 2 comma 9 comma 6 comma 4 comma 3 comma and 8 without repetition? for example, 664 is not allowed.
Answers: 1
question
Mathematics, 21.06.2019 23:30
The table shows the number of hours orlando spent at football practice last week. select the appropriate numbers below to complete the model to find the number of hours orlando spent practicing on tuesday and friday.
Answers: 2
You know the right answer?
If 4 labourers can finish a job in 6days how long would it take 3men to do the job
​...
Questions
question
English, 16.12.2020 01:00
question
Mathematics, 16.12.2020 01:00
question
Social Studies, 16.12.2020 01:00
Questions on the website: 13722362