A contractor's project being analyzed by PERT has an estimated time for the critical path of 120 days. The sum of all activity variances is 81; the sum of variances along the critical path is 64.
(1) What is the probability that the project will take 130 or more days to complete?
(2) What is the probability that the project will take 108 or less days to complete?
(3) What is the probability that the project will be finished between 108 and 130 days?
(4) Please identify and date by which the project will be finished with a 99% probability.
Answers: 2
Mathematics, 21.06.2019 17:00
Asocial networking site currently has 400,000 active members, and that figure is predicted to increase by 32% each year. the following expression represents the number of active members on the site after t years.
Answers: 1
Mathematics, 21.06.2019 18:00
Describe the relationship between the angles of similar triangles and the sides of similar triangles
Answers: 1
Mathematics, 21.06.2019 18:00
The sat and act tests use very different grading scales. the sat math scores follow a normal distribution with mean 518 and standard deviation of 118. the act math scores follow a normal distribution with mean 20.7 and standard deviation of 5. suppose regan scores a 754 on the math portion of the sat. how much would her sister veronica need to score on the math portion of the act to meet or beat regan's score?
Answers: 1
Mathematics, 21.06.2019 19:00
If (x-2) 2= 49, then x could be a. -9 b. -7 c.- 2 d. 5 e.9
Answers: 2
A contractor's project being analyzed by PERT has an estimated time for the critical path of 120 day...
Mathematics, 29.07.2020 02:01
History, 29.07.2020 02:01
Biology, 29.07.2020 02:01