A construction project has four separate components that must be completed in order. The expected values and standard deviations of the completion times of the activities are listed below. Assuming that the four activities are independent, determine the expected value and standard deviation of the completion time of the project.
Activity Expected Completion Time (Days) std. Dev.
1 17 6
2 12 3
3 26 4
4 7 2
Expected value of completion time of project =
Standard deviation of completion time of project =
Answers: 1
Mathematics, 21.06.2019 21:40
Scores on the cognitive scale of the bayley-scales of infant and toddler development range from 1 to 19, with a standard deviation of 3. calculate the margin of error in estimating the true mean cognitive scale score, with 99% confidence, if there are 12 infants and toddlers in a sample.
Answers: 3
Mathematics, 21.06.2019 23:00
Square a has a side length of (2x-7) and square b has a side length of (-4x+18). how much bigger is the perimeter of square b than square a?and show all work! you so
Answers: 2
Mathematics, 22.06.2019 00:00
28 x 12 + 34 = ? it's for a test that if i fail on i will not proceed into the honor roll society i always dreamed of!me! worth 50 !
Answers: 1
A construction project has four separate components that must be completed in order. The expected va...
History, 06.12.2019 22:31
Computers and Technology, 06.12.2019 22:31