A can do a piece of work in 15 days. B can do the same work in 12 days and C can
finish the same piece of work in 20 days. They started the work together for 2 days
and then B and C leaves. In how many days will A finish the remaining work?
Answers: 1
Mathematics, 21.06.2019 13:30
Ily begins solving the equation 4(x – 1) – x = 3(x + 5) – 11. her work is shown below. 4(x – 1) – x = 3(x + 5) – 11 4x – 4 – x = 3x + 15 – 11 3x – 4 = 3x + 4 how can her partial solution be interpreted?
Answers: 2
Mathematics, 21.06.2019 22:30
At the beginning of year 1, carlos invests $600 at an annual compound interest rate of 4%. he makes no deposits to or withdrawals from the account. which explicit formula can be used to find the account's balance at the beginning of year 5? what is, the balance?
Answers: 2
Mathematics, 21.06.2019 23:30
Scenario: susan wants to make 2 square flags to sell at a crafts fair. the fabric she wants to buy is 3 meters wide. she doesn't want any fabric left over. what's the least amount of fabric she should buy? question: which equation will susan solve her problem? note: let x represent the length of 1 side of the flag. options: 1) 2x^2 = 4x 2) 8 +2x = 2(4x) 3) 2 * 2 = 4 * 2 4) 4x^2 -2x = 0
Answers: 2
A can do a piece of work in 15 days. B can do the same work in 12 days and C can
finish the same pi...
Mathematics, 15.04.2021 19:40
Mathematics, 15.04.2021 19:40
Mathematics, 15.04.2021 19:40
English, 15.04.2021 19:40
Chemistry, 15.04.2021 19:40
Mathematics, 15.04.2021 19:40
Physics, 15.04.2021 19:40
Engineering, 15.04.2021 19:40
Mathematics, 15.04.2021 19:40
Mathematics, 15.04.2021 19:40