Mathematics, 04.08.2021 18:00 rileyeddins1010

A man contracts to construct a school building in 20 days and employs 16 men on it immediately. At the end of 12 days the work is only half done. What additional number of men must he employ to fulfill the contract ?​

ansver
Answers: 3

Another question on Mathematics

question
Mathematics, 21.06.2019 12:30
Regular price is $77.00 and the discount is 5% find the sale price
Answers: 3
question
Mathematics, 21.06.2019 15:10
Point a is located at (0, 4), and point c is located at (−3, 5). find the x value for the point b that is located one fourth the distance from point a to point c. −0.25 −0.5 −0.75 −1
Answers: 1
question
Mathematics, 21.06.2019 16:30
An equation where variables are used to represent known values—function notation true or false
Answers: 2
question
Mathematics, 21.06.2019 23:40
Klmn and pqrs are similar trapezoids. which side of pqrs corresponds to lm
Answers: 1
You know the right answer?
A man contracts to construct a school building in 20 days and employs 16 men on it immediately. At t...
Questions
question
Mathematics, 31.10.2021 03:30
question
English, 31.10.2021 03:30
question
Mathematics, 31.10.2021 03:40
question
Mathematics, 31.10.2021 03:40
Questions on the website: 13722360