Mathematics, 05.08.2021 17:30 elijahjacksonrp6z2o7

A can do a piece of work in 3 days and B in 6 days andShyam in 12 days. In how many days will they finish it when both work at it.​

ansver
Answers: 1

Another question on Mathematics

question
Mathematics, 21.06.2019 23:30
If the perimeter of the garden is 37 ft. the width is x and the length is 15 ft. what is the width of the garden in feet?
Answers: 2
question
Mathematics, 21.06.2019 23:30
Hundred and tens tables to make 430 in five different ways
Answers: 1
question
Mathematics, 22.06.2019 01:00
X^2/100+y^2/25=1 the length of the major axis is: a)5 b)10 c)20
Answers: 3
question
Mathematics, 22.06.2019 02:00
Point a is at 12, and point d is at 56. point c is midway between a and d, and point b is midway between a and c. which of these is the coordinate of b?
Answers: 3
You know the right answer?
A can do a piece of work in 3 days and B in 6 days andShyam in 12 days. In how many days will they f...
Questions
question
Mathematics, 23.02.2021 21:40
question
Mathematics, 23.02.2021 21:40
question
Mathematics, 23.02.2021 21:40
question
Mathematics, 23.02.2021 21:40
question
Mathematics, 23.02.2021 21:50
Questions on the website: 13722363