Invers proportion it takes 12 workers 3 weeks to complete four project. each project take same numbers of hours

a) at this rate how long would it take fifteen workers to complete ten project? = 6 weeks

b) the ten projects need to be completed in under four weeks. what is the minimum number of workers be needed, given that they all work at the same rate as the original workers ? ( i know answer i need axplaning ) :]

ansver
Answers: 2

Another question on Mathematics

question
Mathematics, 21.06.2019 17:00
Which set of reflections would carry trapezoid abcd onto itself? a) x-axis, y=x, y-axis, x-axis b) x-axis, y-axis, x-axis c) y=x, x-axis, x-axis d) y-axis, x-axis, y-axis, x-axis
Answers: 2
question
Mathematics, 21.06.2019 19:30
Solve the following inequalities and show the solution on a number line. 3/4 (2x-7) ≤ 5
Answers: 1
question
Mathematics, 21.06.2019 20:00
The multiplicative property of equality states that for real numbers a, b, c, and d, if a = b and c = d, then ac = bd. true false
Answers: 1
question
Mathematics, 21.06.2019 21:30
Carl's candies has determined that a candy bar measuring 3 inches long has a z-score of +1 and a candy bar measuring 3.75 inches long has a z-score of +2. what is the standard deviation of the length of candy bars produced at carl's candies?
Answers: 1
You know the right answer?
Invers proportion it takes 12 workers 3 weeks to complete four project. each project take same numb...
Questions
question
Mathematics, 12.04.2021 18:40
question
Mathematics, 12.04.2021 18:40
Questions on the website: 13722363