Question 4 (5 marks) To restore a vintage train, 13 activities need to be completed. The network below shows these 13 activities and their completion times in hours. C,6 G, 3 4,5 1D, 2 H,4 K,7 E, 2 L, 3 start finish B, 5 F,4 1,3 *M,6 J, 2 a. Determine the earliest starting time of activity F.

The minimum time in which all 13 activities can be completed is 21 hours.
b. What is the latest starting time of activity L?

C. What is the float time of activity J?

Just before they started restoring the train, the members of the club needed to add another activity, X, to the project Activity X will take seven hours to complete. Activity X has no predecessors, but must be completed before activity G starts.
d. What is the latest starting time of activity Xif it is not to increase the minimum completion time of the project? 1 mark​

ansver
Answers: 2

Another question on Mathematics

question
Mathematics, 21.06.2019 14:30
Find the value of tan theta if sin theta = 12/13 and theta is in quadrant 2
Answers: 3
question
Mathematics, 21.06.2019 18:30
Which equation represents the model shown? a)1/3 divide 1/6 = 2 b)2/3 divide 1/6 = 2/18 c)1/3 divide 1/6 = 1/18 d)2/3 divide 1/6 =4
Answers: 1
question
Mathematics, 21.06.2019 19:00
Acomputer store bought a program at a cost of $10 and sold it for $13. find the percent markup
Answers: 1
question
Mathematics, 21.06.2019 19:30
Aproduction manager test 10 toothbrushes and finds that their mean lifetime is 450 hours. she then design sales package of this type of toothbrush. it states that the customers can expect the toothbrush to last approximately 460 hours. this is an example of what phase of inferential statistics
Answers: 1
You know the right answer?
Question 4 (5 marks) To restore a vintage train, 13 activities need to be completed. The network bel...
Questions
question
English, 19.08.2020 14:01
question
Mathematics, 19.08.2020 14:01
question
English, 19.08.2020 14:01
Questions on the website: 13722367