1) 15 men can do a piece of work in 80 days. How long will it take to finish the work if 5 men were added? 2)If 24 workers can complete a piece of work in 42 days. How many workers should be added to complete the same work in 18 days.

step by step

ansver
Answers: 3

Another question on Mathematics

question
Mathematics, 21.06.2019 16:40
Which region represents the solution to the given system of inequalities? |-0.5x+y23 | 1.5x+ys-1 5 4 -3 -2 -1 1 2 3 4
Answers: 1
question
Mathematics, 21.06.2019 21:00
Ade and abc are similar. which best explains why the slope of the line between points a and d is the same as the slope between points a and b?
Answers: 2
question
Mathematics, 21.06.2019 21:10
The vertices of a triangle are a(7.5), b(4,2), and c19. 2). what is
Answers: 1
question
Mathematics, 21.06.2019 23:30
In the diagram, ab is tangent to c, ab = 4 inches, and ad = 2 inches. find the radius of the circle.
Answers: 3
You know the right answer?
1) 15 men can do a piece of work in 80 days. How long will it take to finish the work if 5 men were...
Questions
Questions on the website: 13722363