you are planning to use PERT for planning of your project. A task has pessimistic estimate of 24 days, most likely estimate of 15 days and optimistic estimate of 12 days. what is the mean using the PERT technique

ansver
Answers: 2

Another question on Mathematics

question
Mathematics, 21.06.2019 16:30
Ivan and jeff buy a package of 8 pens for $4.00. ivan wants 5 of the pens, and jeff wants 3.how much should each student pay?
Answers: 1
question
Mathematics, 21.06.2019 18:30
What is the result of converting 60 ounces to pounds remember there are 16 ounces in a pound
Answers: 2
question
Mathematics, 21.06.2019 21:00
5x−4≥12 or 12x+5≤−4 can you with this problem
Answers: 3
question
Mathematics, 22.06.2019 00:30
One positive integer is 2 less than another. the product of the two integers is 24. what are the integers
Answers: 1
You know the right answer?
you are planning to use PERT for planning of your project. A task has pessimistic estimate of 24 day...
Questions
question
Health, 30.03.2020 18:56
question
Mathematics, 30.03.2020 18:57
question
Spanish, 30.03.2020 18:57
Questions on the website: 13722360