Mathematics, 18.01.2022 01:00 isaiahb30

Cory, Amanda, and Bryan together need a total of 9 days to finish painting the house. Amanda and Bryan together need 12 days to finish painting. How many days will it take for Cory to paint the house alone?

ansver
Answers: 1

Another question on Mathematics

question
Mathematics, 21.06.2019 16:20
Match each statement with its corresponding value for the system below: y = -2(3)x and y = 9x - 2 1. the number of points of intersection. -2 2. the x-coordinate of the solution. 1 3. the y-coordinate of the solution. 0
Answers: 3
question
Mathematics, 21.06.2019 16:30
Iwant to know what 3g+5h+4g-2h is my teacher is too selfish to tell us
Answers: 1
question
Mathematics, 21.06.2019 22:30
Which term below correctly completes the following sentence? if a function has a vertical asymptote at a certain x value, then the function is what at that value
Answers: 1
question
Mathematics, 21.06.2019 23:30
Find the measure of angle y. round your answer to the nearest hundredth. ( type the numerical answer only) a right triangle is shown with one leg measuring 5 and another leg measuring 14. an angle across from the leg measuring 5 is marked y degrees. numerical answers expected!
Answers: 1
You know the right answer?
Cory, Amanda, and Bryan together need a total of 9 days to finish painting the house. Amanda and Bry...
Questions
question
Chemistry, 25.11.2019 00:31
question
Social Studies, 25.11.2019 00:31
question
Mathematics, 25.11.2019 00:31
Questions on the website: 13722363