(Unitary Method) 12 workers can do a piece of work in 20 days. How many workers should be added to complete the work in 16 days?
(Give answer in process by process)
(Answer is 3 workers)

ansver
Answers: 3

Another question on Mathematics

question
Mathematics, 21.06.2019 19:30
Acylinder with a base diameter of x units has a volume of jxcubic units which statements about the cylinder are true? check all that apply. the radius of the cylinder is 2 x units. the radius of the cylinder is 2x units. the area of the cylinder's base is 200 square units. the area of the cylinder's base is a square units. the height of the cylinder is 2x units. the height of the cylinder is 4x units. mark this and return save and exit next submit
Answers: 2
question
Mathematics, 21.06.2019 21:30
Can someone explain to me how to do
Answers: 1
question
Mathematics, 21.06.2019 22:10
Akitchen is 12 ft. by 14 ft. with 10 ft. high walls. how much would it cost to put vinyl flooring in this room? $8.80 per ft
Answers: 1
question
Mathematics, 21.06.2019 22:30
An ant travels at a constant rate of 30cm every 2 minutes.at what speed does the ant travel per minute
Answers: 2
You know the right answer?
(Unitary Method) 12 workers can do a piece of work in 20 days. How many workers should be added to...
Questions
question
Chemistry, 06.12.2019 05:31
question
Mathematics, 06.12.2019 05:31
question
Spanish, 06.12.2019 05:31
question
Mathematics, 06.12.2019 05:31
question
Mathematics, 06.12.2019 05:31
Questions on the website: 13722361