Mathematics, 24.02.2022 20:10 Cullan2383

When building a house, the number of days required to build is inversely proportional to with the number of workers. One house was built in 10 days
by 44 workers. How many days would it take to build a similar house with 5
workers?

ansver
Answers: 1

Another question on Mathematics

question
Mathematics, 21.06.2019 15:20
Which is the equation of an ellipse with directrices at x = ±4 and foci at (2, 0) and (−2, 0)?
Answers: 3
question
Mathematics, 21.06.2019 16:00
You eat 8 strawberries and your friend eats 12 strawberries from a bowl. there are 20 strawberries left. which equation and solution give the original number of strawberries?
Answers: 3
question
Mathematics, 21.06.2019 17:20
Consider the proof. given: segment ab is parallel to line de. prove: what is the missing statement in step 5?
Answers: 2
question
Mathematics, 21.06.2019 22:10
Gravel is being dumped from a conveyor belt at a rate of 25 ft3/min, and its coarseness is such that it forms a pile in the shape of a cone whose base diameter and height are always equal. how fast is the height of the pile increasing when the pile is 14 ft high? (round your answer to two decimal places.) ft/min
Answers: 3
You know the right answer?
When building a house, the number of days required to build is inversely proportional to with the...
Questions
question
Mathematics, 10.02.2021 14:00
question
Mathematics, 10.02.2021 14:00
question
Mathematics, 10.02.2021 14:00
question
Mathematics, 10.02.2021 14:00
question
Mathematics, 10.02.2021 14:00
question
Mathematics, 10.02.2021 14:00
question
Mathematics, 10.02.2021 14:00
question
Mathematics, 10.02.2021 14:00
Questions on the website: 13722360