Pessimistic time refers to:

A. the maximum period of time for an activity to be completed.
B. the minimum period of time for an activity to be completed.
C. the planner's "best guess" of the amount of time the activity actually will require for completion.
D. the maximum period of time for an entire project to be completed.
E. the average period of time for an activity to be completed.

ansver
Answers: 2

Another question on Social Studies

question
Social Studies, 22.06.2019 07:00
1of the following choices, which one best describes one way that christianity came to east africa? a. christians traveled in caravans through the sahara desert and introduced the people of mali to a new religion. b. christian traders from the mediterranean interacted with the people of axum. c. christian military from west africa traveled across the continent to bring their religion to the people of east africa. d. christian rulers from asia traveled to east africa to bring their religion to the people. 2 which trade item from outside the region did west africans need most? a. gold b. camels c. salt d. iron
Answers: 2
question
Social Studies, 22.06.2019 11:00
This form of government has only a single political party. question 2 options: communist democratic autocratic parliamentary
Answers: 1
question
Social Studies, 22.06.2019 11:40
The president’s role in a political party is to set the legislative agenda true or false
Answers: 1
question
Social Studies, 22.06.2019 22:00
How can the judiciary balance individual rights with the common good?
Answers: 1
You know the right answer?
Pessimistic time refers to:

A. the maximum period of time for an activity to be complete...
Questions
question
Biology, 19.11.2020 22:00
question
Chemistry, 19.11.2020 22:00
question
Mathematics, 19.11.2020 22:00
question
Mathematics, 19.11.2020 22:00
question
History, 19.11.2020 22:00
Questions on the website: 13722360