When the length of critical path of a project is 40 days and the variance of the project is 4 days, what due date should be set for this project so that the probability of completing the project is 95%? since it is on days, round the answer to the nearest higher integer. the z value of 95% is 1.645.

ansver
Answers: 1

Another question on Business

question
Business, 21.06.2019 20:30
Elizabeth believes her company has discriminated against her because her minority coworkers, who are less qualified, have been promoted ahead of her. which agency should elizabeth contact? - national alliance of business- affirmative action council- equal employment opportunity commission- federal trade commission- fair employment practices agency
Answers: 2
question
Business, 22.06.2019 09:20
Which statement best defines tuition? tuition is federal money awarded to a student. tuition is aid given to a student by an institution. tuition is money borrowed to pay for an education. tuition is the price of attending classes at a school.
Answers: 1
question
Business, 22.06.2019 10:10
At the end of year 2, retained earnings for the baker company was $3,550. revenue earned by the company in year 2 was $3,800, expenses paid during the period were $2,000, and dividends paid during the period were $1,400. based on this information alone, retained earnings at the beginning of year 2 was:
Answers: 1
question
Business, 22.06.2019 22:50
Wendy made her career planning timeline in 2010. in what year should wendy's timeline start? a. 2013 o b. 2012 oc. 2010 o d. 2011
Answers: 2
You know the right answer?
When the length of critical path of a project is 40 days and the variance of the project is 4 days,...
Questions
question
Mathematics, 22.05.2020 22:06
question
Mathematics, 22.05.2020 22:06
question
History, 22.05.2020 22:07
question
Mathematics, 22.05.2020 22:07
Questions on the website: 13722363