An assembly line with 30 activities is to be balanced. the total amount of time required for all 30 activities is 45 minutes. the line will operate for 420 minutes per day. which of the following must be the cycle time to achieve an output rate of 300 units/day?

a. 0.80 minutes
b.1.4 minutes
c. 2.4 minutes
d. 3.0 minutes

ansver
Answers: 3

Another question on Business

question
Business, 22.06.2019 00:20
Suppose that the world price of steel is $100 a ton, india does not trade internationally, and the equilibrium price of steel in india is $60 a ton. suppose that india now begins to trade internationally. the price of steel in india the quantity of steel produced in india a. does not change; does not change b. falls; increases c. falls; decreases d. rises; decreases e. rises; increases the quantity of steel bought by india india steel. a. increases; exports b. decreases; imports c. decreases; exports d. does not change; neither imports nor exports e. increases; imports
Answers: 2
question
Business, 22.06.2019 05:30
Find a company that has followed a strong strategic direction- state that generic strategy and the back-up points to support your position.
Answers: 1
question
Business, 22.06.2019 19:40
Moody corporation uses a job-order costing system with a plantwide predetermined overhead rate based on machine-hours. at the beginning of the year, the company made the following estimates: machine-hours required to support estimated production 100,000 fixed manufacturing overhead cost $ 650,000 variable manufacturing overhead cost per machine-hour $ 3.00 required: 1. compute the plantwide predetermined overhead rate. 2. during the year, job 400 was started and completed. the following information was available with respect to this job: direct materials $ 450 direct labor cost $ 210 machine-hours used 40
Answers: 3
question
Business, 22.06.2019 21:00
You are given the following information about aggregate demand at the existing price level for an economy: (1) consumption = $400 billion, (2) investment = $40 billion, (3) government purchases = $90 billion, and (4) net export = $25 billion. if the full-employment level of gdp for this economy is $600 billion, then what combination of actions would be most consistent with closing the gdp gap here?
Answers: 3
You know the right answer?
An assembly line with 30 activities is to be balanced. the total amount of time required for all 30...
Questions
Questions on the website: 13722361