Given this project and the requirement that the number of resources working on a task cannot be less than the number assigned to the task, answer the following question. If the tasks were placed in a serial relationship with Task 1 first and the others in numerical order, on what day would Task 3 be done?
a) day 18
b) day 3
c) day 10

ansver
Answers: 1

Another question on Business

question
Business, 21.06.2019 23:30
Which term refers to the cost that motivates an economic decision
Answers: 1
question
Business, 22.06.2019 01:00
Awidower devised his fee simple interest in his residence as follows: “to my daughter for life, then to my oldest grandchild who survives her.” at the time of the widower’s death, he was survived by his only two children, a son and a daughter, and by one grandchild, his daughter’s son. a short time later, the daughter together with her son entered into a contract to sell the residence in fee simple to a buyer. the applicable jurisdiction continues to follow the common law rule against perpetuities, but has abrogated the rule in shelley’s case. at the closing, the buyer refused to purchase the residence. can the sellers compel the buyer to do so?
Answers: 2
question
Business, 23.06.2019 00:10
Many years ago, sprint telecommunications aired an advertisement intended to demonstrate the clarity of reception sprint customers could expect. the ad showed a rancher, who had used a different company, complaining that he had ordered 100 oxen from his supplier and instead received 100 dachshunds. the mix-up was probably due to the presence of in the communication process.
Answers: 3
question
Business, 23.06.2019 08:00
Which sentence in the passage refers to the "analysis" of a given problem? jeremy is the production manager in a manafacturing company. he has identified a problem in the production process. he has estimated that the problem would lead to a loss of $10,000 and would require time to resolve. further, he has also identified the source of the problem to be the outdated machinery, which might require major repair, if not immediate replacement. finally, jeremy has also divided the problem into smaller parts, such as production costs, overheads, downtime expense, repair expenditure, and so on.
Answers: 2
You know the right answer?
Given this project and the requirement that the number of resources working on a task cannot be less...
Questions
Questions on the website: 13722363