"An assembly line consists of 21 tasks grouped into 5 workstations. The sum of the 21 task times is 90 minutes. The largest assigned cycle time is 20 minutes. What is the efficiency of this line?"

ansver
Answers: 2

Another question on Business

question
Business, 22.06.2019 12:20
Over the past decade, brands that were once available only to the wealthy have created more affordable product extensions, giving a far broader range of consumers a taste of the good life. jaguar, for instance, launched its x-type sedan, which starts at $30,000 and is meant for the "almost rich" consumer who aspires to live in luxury. by marketing to people who desire a luxurious lifestyle, jaguar is using:
Answers: 3
question
Business, 22.06.2019 15:20
Kelso electric is debating between a leveraged and an unleveraged capital structure. the all equity capital structure would consist of 40,000 shares of stock. the debt and equity option would consist of 25,000 shares of stock plus $280,000 of debt with an interest rate of 7 percent. what is the break-even level of earnings before interest and taxes between these two options?
Answers: 2
question
Business, 22.06.2019 16:30
On april 1, the cash account balance was $46,220. during april, cash receipts totaled $248,600 and the april 30 balance was $56,770. determine the cash payments made during april.
Answers: 1
question
Business, 22.06.2019 21:00
On july 2, year 4, wynn, inc., purchased as a short-term investment a $1 million face-value kean co. 8% bond for $910,000 plus accrued interest to yield 10%. the bonds mature on january 1, year 11, and pay interest annually on january 1. on december 31, year 4, the bonds had a fair value of $945,000. on february 13, year 5, wynn sold the bonds for $920,000. in its december 31, year 4, balance sheet, what amount should wynn report for the bond if it is classified as an available-for-sale security?
Answers: 3
You know the right answer?
"An assembly line consists of 21 tasks grouped into 5 workstations. The sum of the 21 task times is...
Questions
Questions on the website: 13722360