ou are developing a performance progress report for a project you are managing. The following time-phased budget was developed earlier in the planning stage and is being used as the standard against which the project performance is measured. Work Packages W1 W2 W3 W4 W5 W6 W7 W8 W9 W10 W11 A 10 6 6 B 10 5 5 C 2 7 3 8 6 Total 10 6 6 10 5 5 2 7 3 8 6 You are analyzing the project performance at the end of Week 5. Activity "B" is 40% complete and its actual cost is 15. What is the Schedule Performance Index of this activity? Use two decimal places in your calculations.

ansver
Answers: 3

Another question on Business

question
Business, 22.06.2019 03:00
1) u.s. real gdp is substantially higher today than it was 60 years ago. what does this tell us, and what does it not tell us, about the well-being of u.s. residents? what are the limitations of the gdp as a measure of economic well-being? given the limitations, why is gdp usually regarded as the best single measure of a society’s economic well-being? 2) what is an intermediate good? how does an intermediate good differ from a final good? explain why it is the case that the value of intermediate goods produced and sold during the year is not included directly as part of gdp, but the value of intermediate goods produced and not sold is included directly as part of gdp.
Answers: 2
question
Business, 22.06.2019 11:20
Aborrower takes out a 30-year adjustable rate mortgage loan for $200,000 with monthly payments. the first two years of the loan have a "teaser" rate of 4%, after that, the rate can reset with a 5% annual payment cap. on the reset date, the composite rate is 6%. what would the year 3 monthly payment be?
Answers: 3
question
Business, 22.06.2019 19:00
12. to produce a textured purée, you would use a/an a. food processor. b. wide-mesh sieve. c. immersion blender d. food mill.
Answers: 1
question
Business, 22.06.2019 21:00
The purpose of the transportation approach for location analysis is to minimize which of the following? a. total costsb. total fixed costsc. the number of shipmentsd. total shipping costse. total variable costs
Answers: 1
You know the right answer?
ou are developing a performance progress report for a project you are managing. The following time-p...