Business, 19.10.2021 01:30 amoakoh800003

A manager is an app tempting to put together an aggregate plan for the coming year. She has obtained a forecast of expected demand for the planning horizon. The plan must deal with highly seasonal demand as can be seen from the following forecasts: Period 1 2 3 4 5 6 7 8 9
Forecasts demand (units) 190 230 260 280 210 170 160 260 180

The department has 20 full-time operators, each of whom can produce 10 units of output per period. Starting inventory is 40 units and 20% is safety stock.

Cost
Inventory holding cost $5 per unit
Hiring and training cost $300 per worker
Layoff cost $500 per worker
Cost of subcontracting $30 per unit
Regular-time cost $4 per hour
Overtime cost $6 per hour
Backlog cost $10 per unit
A. Determine the total cost of the plan for strategies as below:
a. Hiring and firing, no overtime
b. Constant workforce
c. Subcontracting
B. Which strategy provided the lowest cost?

ansver
Answers: 1

Another question on Business

question
Business, 22.06.2019 04:30
Annuity payments are assumed to come at the end of each payment period (termed an ordinary annuity). however, an exception occurs when the annuity payments come at the beginning of each period (termed an annuity due). what is the future value of a 13-year annuity of $2,800 per period where payments come at the beginning of each period? the interest rate is 9 percent. use appendix c for an approximate answer, but calculate your final answer using the formula and financial calculator methods. to find the future value of an annuity due when using the appendix tables, add 1 to n and subtract 1 from the tabular value. for example, to find the future value of a $100 payment at the beginning of each period for five periods at 10 percent, go to appendix c for n = 6 and i = 10 percent. look up the value of 7.716 and subtract 1 from it for an answer of 6.716 or $671.60 ($100 × 6.716)
Answers: 2
question
Business, 22.06.2019 07:20
Richardson hired j.c. flood company, a plumbing contractor, to correct a stoppage in the sewer line of her house. the plumbing company's 'snake' device, used to clear the line leading to the main sewer, became caught in the underground line. to release it, the company excavated a portion of the sewer line in richardson's backyard. in the process, the company discovered numerous leaks in a rusty, defective water pipe that ran parallel with the sewer line. to meet public regulations, the water pipe, of a type no longer approved for such service, had to be replaced either then or later, when the yard would have to be excavated again. the plumbing company proceeded to repair the water pipe. though richardson inspected the company's work daily and did not express any objection to the extra work involved in replacing the water pipe, she refused to pay any part of the total bill after the company completed the entire operation. j.c. flood company then sued richardson for the costs of labor and material it had furnished. (c) for what, if anything, should richardson be liable? explain."
Answers: 1
question
Business, 22.06.2019 09:40
As related to a company completing the purchase to pay process, is there an accounting journal entry "behind the scenes" when xyz company pays for the goods within 10 days of the invoice (gross method is used for discounts and terms are 2/10 net 30) that updates the general ledger?
Answers: 3
question
Business, 22.06.2019 10:30
You meet that special person and get married. amazingly your spouse has exactly the same income you do 47,810. if your tax status is now married filing jointly what is your tax liability
Answers: 2
You know the right answer?
A manager is an app tempting to put together an aggregate plan for the coming year. She has obtained...
Questions
question
Mathematics, 25.09.2019 03:00
question
Mathematics, 25.09.2019 03:00
question
Mathematics, 25.09.2019 03:00
question
Social Studies, 25.09.2019 03:00
question
Mathematics, 25.09.2019 03:00
Questions on the website: 13722362