Oxford Company has limited funds available for investment and must ration the funds among four competing projects. Selected information on the four projects follows: Project Investment Required Present value of Cash Inflows Life of the Project (years) Internal Rate of Return A $ 150,000 $ 274,323 7 15% B $ 129,000 $ 247,000 12 20% C $ 103,000 $ 205,035 7 19% D $ 160,000 $ 283,136 3 18% The net present values should be computed using a 10% discount rate. The company wants your assistance in determining which project to accept first, second, and so forth.
Required:
1. Compute the project profitability index for each project.
2. In order of preference, rank the four projects in terms of net present value, project profitability index and internal rate of return.

ansver
Answers: 2

Another question on Business

question
Business, 21.06.2019 19:20
You manage an equity fund with an expected risk premium of 10% and a standard deviation of 14%. the rate on treasury bills is 6%. your client chooses to invest $60,000 of her portfolio in your equity fund and $40,000 in a t-bill money market fund. what is the expected return and standard deviation of return on your client’s portfolio?
Answers: 1
question
Business, 22.06.2019 19:30
Anew firm is developing its business plan. it will require $615,000 of assets, and it projects $450,000 of sales and $355,000 of operating costs for the first year. management is reasonably sure of these numbers because of contracts with its customers and suppliers. it can borrow at a rate of 7.5%, but the bank requires it to have a tie of at least 4.0, and if the tie falls below this level the bank will call in the loan and the firm will go bankrupt. what is the maximum debt ratio the firm can use? (hint: find the maximum dollars of interest, then the debt that produces that interest, and then the related debt ratio.)a. 41.94%b. 44.15%c. 46.47%d. 48.92%e. 51.49%
Answers: 3
question
Business, 22.06.2019 22:00
The following table gives the map coordinates and the shipping loads for a set of cities that we wish to connect through a central hub.,(7,(4,(7,(6,(2,( 2,) for the location of the proposed new central hub, the coordinates should be near: x==) if the shipments from city a double, for the location of the proposed new central hub, the coordinates should be near: x==.926.865.017.21
Answers: 1
question
Business, 23.06.2019 00:00
Which of the following statements is true about an atm card?
Answers: 1
You know the right answer?
Oxford Company has limited funds available for investment and must ration the funds among four compe...
Questions
question
History, 05.05.2020 12:56
question
Mathematics, 05.05.2020 12:56
question
Mathematics, 05.05.2020 12:56
question
English, 05.05.2020 12:56
question
English, 05.05.2020 12:56
Questions on the website: 13722363