Six years ago, an 80-kw diesel electric set cost $160,000. the cost index for this class of equipment six years ago was 187 and is now 194. the cost-capacity factor is 0.6. the plant engineering staff is considering a 120-kw unit of the same general design to to power a small isolated plant. assume we want to add a pre-compressor, which (when isolated and estimated separately) currently costs $18,000. determine the total cost of the 120-kw unit.
b. estimate the cost of a 40-kw unit of the same general design. include the cost of the $18,000 precompressor.

ansver
Answers: 1

Another question on Engineering

question
Engineering, 03.07.2019 14:10
Explain the difference laminar and turbulent flow. explain it with the shear stress and the velocity profiles.
Answers: 1
question
Engineering, 03.07.2019 14:10
When at a point two solid phase changes to one solid phase on cooling then it is known as a) eutectoid point b) eutectic point c) peritectic point d) peritectoid point
Answers: 3
question
Engineering, 04.07.2019 18:10
The thermal expansion or contraction of a given metal is a function of the f a)-density b)-initial temperature c)- temperature difference d)- linear coefficient of thermal expansion e)- final temperature f)- original length
Answers: 2
question
Engineering, 04.07.2019 18:10
Water at 55c flows across a flat plate whose surface temperature is held constant at 95c. if the temperature gradient at the plate's surface for a given value of x is 18 c/mm, find a) local heat transfer coefficient. b) heat flux
Answers: 3
You know the right answer?
Six years ago, an 80-kw diesel electric set cost $160,000. the cost index for this class of equipmen...
Questions
question
Spanish, 27.08.2021 17:30
question
Mathematics, 27.08.2021 17:40
question
Mathematics, 27.08.2021 17:40
Questions on the website: 13722360