A project manager has determined that 3/10 of the work for a project was completed in 9 days. How many more days
will it take to finish the project if the work continues to progress at the same rate?

ansver
Answers: 1

Another question on Mathematics

question
Mathematics, 21.06.2019 20:00
Evaluate the discriminant of each equation. tell how many solutions each equation has and whether the solutions are real or imaginary. x^2 - 4x - 5 = 0
Answers: 2
question
Mathematics, 21.06.2019 21:30
Ebuka's monthly rent is $750. if ebuka pays the rent late, his landlord charges 4% interest per week that the payment is late. write a function that gives the total cost r(t), in dollars, of ebuka's rent if he pays it t weeks late.
Answers: 1
question
Mathematics, 21.06.2019 22:00
Consider the triangle. which shows the order of the angles from smallest to largest? angle a, angle b, angle c angle b, angle a, angle c angle b, angle c, angle a angle c, angle a, angle b
Answers: 3
question
Mathematics, 22.06.2019 02:00
Write the component forms of vectors u and v, shown in the graph, and find v − 2u. u= (< -3, -2> , < -3, -1> , < -2, -2> , < -2, -1> ) v= (< -5, 1> , -4, 0> , < 0, -4> , < 1, -5> ) v-2u= (< 5, 3> , < 0, 4> , < 4, 0> , < 5, -3>
Answers: 3
You know the right answer?
A project manager has determined that 3/10 of the work for a project was completed in 9 days. How ma...
Questions
question
Spanish, 30.11.2019 18:31
Questions on the website: 13722362